Regional Ministry for Infrastructure and Transport - Valencia (Spain)
SCOPE OF THE WORKS
The Regional Ministry for Public Works (Conselleria d’Infrastructures i Transports) has planned the CV-30 ring road as a north eastern distributor road of those areas closest to the city of Valencia. Currently, the section running from the connection between the V-30 and the west slip road in Quart de Poblet to the Maestro Rodrigo junction is already built and in service.
TASKS PERFORMED
- Study of the works contract documents
- Review of the project
- Works logbook
- Check for changes in the specifications
- Check building equipment
- List the constructor workers and employees
- Revision and approval of minutes
- Unified awards for concepts in extra works
- Environmental management supervision
- Quality control at work
WORKS DESCRIPTION
Of all the works included in the project, two are worth highlighting:
- STRUCTURES ON THE LLIRIA HIGHWAY INTERSECTION: Planned as a two-level directional intersection, this is a mixed double structure measuring 106 metres in length, with three spans of 32, 42 and 32 metres, and a mixed structure curving over 84 metres in four openings for the turning slip road on an intermediate height between the North Ring Road and the CV-35.
- METRO AND TRAMWAY UNDERPASS: This was carried out using a 46 metre wide, 32 m long and 6.30 metre high box jack. The box jack was built elsewhere and installed underneath the tram lines in successive stages of provisional stabilising, hydraulic jacks and back-fill covering a total distance of 33 metres.